We are in the FINAL WEEK. We move in this Friday!!!!
Last week, Garrett and I left town on Friday afternoon and didn't see much of the house since the painters were inside painting the cabinets with white lacquer paint that off-gassed lung-burning fumes. When we got back Sunday afternoon, it looked like the painters had also started painting some of the walls.
Today, COUNTER TOPS were installed! WOW.
And Arnold the plumber came back to begin fixture installation. He did some today and will return tomorrow to finish.
Valentin the flooring guy came in late today and completed the flooring in the master bedroom. He will return tomorrow to do the bathroom and kitchen floor.
Sorry for the bad photography - it was dark when I met Garrett at the house and I took some of these in the complete DARK.
Downstairs bath: shower head!
Downstairs bath: counter top!
Downstairs bath: laundry chute
Downstairs bath: trimmed window to tile
Upstairs bath: shower fixtures!
Upstairs bath: TOILET!
Upstairs bath, vanity + toilet
Valentin is filling out the closet with cork!
Closet got painted today!

This closet got painted too!
Kitchen: counter top, sink, faucet, and soap dispenser!
Kitchen: south elevation long view



Kitchen: north elevation long view.



Flooring: the darker color will go into the downstairs bathroom and the lighter color in the kitchen.

Placing one kitchen plank for effect!
 